Contact Us

Cable Trays and Ladder Rack for Panel Feeds

Wire mesh cable trays in three side heights and widths from 100 mm to 600 mm, supplied in 3 m lengths. Ladder rack in 100 mm side height with 300 mm to 600 mm widths, weighed per piece for support planning. Both families are listed with the wire or rung data that sets the load a support span can carry. Splice plates, supports and earthing continuity are quoted with the tray, not left to the installer.
quote now

Product Specifications

Product Overview

A cable tray is a support, not a route. The tray carries the weight of the cables between the brackets, and the bracket spacing is what actually decides whether the run sags. That is why the maker load table is always printed against a stated support span, and why a tray quoted without the span is only half the information.

Wire mesh trays carry more than their weight suggests because the pattern puts the material where the load is. On the Cablofil range the top longitudinal wire and the cross wires are 5.9 mm, and the remaining longitudinal wires are 3.9 mm, so the same mass of steel sits under the cable instead of in a flat sheet. The mesh opening is 50 by 100 mm, which lets a cable leave the tray at any point without cutting.

Ladder rack is chosen when the cables are stiff, when they have to be tied at regular intervals, or when the run needs to be walked on during installation. Rung spacing and side height set the bending, and the mass per piece decides whether two people can lift a 3 m length onto the brackets. On a plant feed the tray is often mesh inside the room and ladder on the roof run.

Key Specifications

FamilyTypeSide heightWidthsStandard lengthMaterial
Cablofil CF54wire mesh tray54 mm100 to 600 mm3 mpre-galvanized steel, stainless on request
Cablofil CF105wire mesh tray105 mm100 to 600 mm3 mpre-galvanized steel, stainless on request
Cablofil CF150wire mesh tray150 mm100 to 600 mm3 mpre-galvanized steel, stainless on request
Niedax KLB and KLBGladder rack, 100 mm side height100 mm300 to 600 mm3 mstrip galvanized, hot dip on request
Niedax KLTAladder rack with perforated side100 mm300 to 400 mm3 mstrip galvanized

Included Models and Order Codes

The part code carries the two dimensions. On Cablofil the first number after CF is the side height in millimetres and the second is the width, so CF105/300 is 105 mm high and 300 mm wide, and the finish suffix sets the coating. On Niedax the six digits after the dash are width and length in decimetres, so KLBK100.303 is 300 mm wide in a 3 m length. Weights are per piece for the ladder and per metre where the maker publishes it, because that is the figure the bracket spacing is checked against.

Part numberTypeSide heightWidthLengthMass
CF54/100Cablofil wire mesh54 mm100 mm3 mon request
CF54/200Cablofil wire mesh54 mm200 mm3 m4.0 kg
CF54/300Cablofil wire mesh54 mm300 mm3 mon request
CF54/450Cablofil wire mesh54 mm450 mm3 mon request
CF105/200Cablofil wire mesh105 mm200 mm3 mon request
CF105/300Cablofil wire mesh105 mm300 mm3 mon request
CF105/600Cablofil wire mesh105 mm600 mm3 m12.9 kg
CF150/200Cablofil wire mesh150 mm200 mm3 m9.1 kg
CF150/300Cablofil wire mesh150 mm300 mm3 mon request
CF150/600Cablofil wire mesh150 mm600 mm3 mon request
KLBK100.303Niedax ladder rack100 mm300 mm3 m11.8 kg, 3.9 kg/m
KLBK100.603Niedax ladder rack100 mm600 mm3 m23.6 kg
KLBG100.403Niedax ladder rack100 mm400 mm3 m15.7 kg
KLBG100.503Niedax ladder rack100 mm500 mm3 m19.7 kg
KLTA100.303Niedax ladder rack, perforated side100 mm300 mm3 m11.8 kg

Key Features

Three side heights on one width range – 54, 105 and 150 mm side height share the same splice plates and supports, so a run can change depth at a pull box without new hardware.

Wire size follows the load path – 5.9 mm on the top longitudinal and cross wires, 3.9 mm on the rest, which is where the load capacity comes from on a mesh tray.

Open mesh for cable entry – 50 by 100 mm openings allow a cable to leave at any point along the run, including after the tray is fixed.

Ladder side height at 100 mm – a stiff side member with a rolled edge, used where the run is long, the cables are armoured, or the tray has to be walked on.

Cut and bend on site – mesh tray is cut with a saw and joined with a splice plate, so a change of direction does not need a made to order fitting.

Earthing continuity as a line item – the splice plate and the earthing terminal are quoted with the tray, because the continuity of the run is part of the installation acceptance.

Applications

Tray and ladder are chosen by the run, not by the room. Three patterns cover most plant work.

Machine feed inside a production hall – 54 mm mesh tray on 1.5 m brackets, with cables leaving through the mesh at each machine instead of through drilled holes.

Panel to panel cable routes – 105 mm mesh tray above the cabinet row, sized so the fill stays under half the tray depth and the door swing is clear.

Roof and outdoor runs – ladder rack with hot dip finish on wider supports, because the span between roof posts is longer than a wall bracket spacing.

Tray runs are quoted with the panels they feed, so the SUPERB PCBA and the SUPERB PCB are checked against the same cable schedule and the tray width is set after the harness is fixed.

Sourcing and Cross-Reference

Start from the cable schedule, not from the tray. Sum the cable diameters into a fill, keep the fill at about half the side height so the cables are not crushed by the cover, and only then pick the width. A 300 mm tray that is filled to the top acts as a single stiff bundle and its real load capacity drops below the table value.

Set the support spacing from the load table at the span you can build. The maker table gives a load per metre for a stated span, and the same tray carries less when the brackets are further apart. On a roof run the posts decide the span, so the tray is chosen after the post spacing, not before.

Watch the material pair at the transition. A galvanized tray bolted to a stainless bracket is fine, and a copper earth bar laid loose inside a galvanized tray is not. Where the run passes from indoor to outdoor, the joint is the place to change finish and to keep the two metals apart.

Lead time on mesh tray follows the finish rather than the size, and a hot dip order is quoted per batch. See lead time and availability for the current position, and shortage recovery when a size is missing from a shipment.

The SUPERB Assembly team ties the harness at the tray exit rather than inside the mesh, because a tie around a 5.9 mm wire rubs through the jacket on a vibrating run.

Q: Can you supply the tray, the splice plates and the wall brackets as one delivery sized to our cable schedule?

A: Yes. Send the cable schedule with diameters and the bracket or post spacing you can build, and the SUPERB Tech team returns the tray size, the finish and the splice plates for the run.

Why Contractors Buy Cable Trays From SUPERB

  1. Tray and support quoted together: the bracket spacing, the splice plate and the earthing terminal are in the same quotation, so the span is not fixed after the tray arrives.
  2. Codes decoded in the table: height and width are shown separately for every part, which removes the reading error that comes from a part code alone.
  3. Mass per piece stated: the weight of a 3 m ladder length is in the table, which decides whether the run is built by two people or by a lift.
  4. Finish matched to the run: indoor runs are quoted pre-galvanized and outdoor runs hot dip, so the change happens at the joint rather than at the end of the project.

Related Product Families

This page is part of the component range we supply for industrial, telecom, medical and defence builds. Continue with: Slotted Wire Duct and Cable Trunking for Panel Wiring, Cable Entry Plates and Brush Grommets for Cabinet Bases, Cable Clamps and Harness Ties for Internal Wiring, Earthing Braids and Bonding Straps, Steel and Aluminium DIN Rails for Control Cabinets.