Material in quarantine is in limbo: received, on the premises, unusable, not yet rejected. The value of the process is not the cage or the yellow tag. It is the decision at the end of it, and whether that decision is written down before the material moves.
What a hold is meant to prove
A hold proves three things: a specific quantity of a specific lot was stopped at a specific time, the reason was recorded in terms another person can check, and the material did not move until someone with authority wrote a disposition.
The cage and the tag exist to make those three facts hard to lose, and none of them substitutes for the decision.
The six reasons material gets held
| Reason for hold | What triggers it | What has to be true before release |
|---|---|---|
| Documentation mismatch | Part number, quantity or maker marking differs from the purchase order | The difference is explained in writing by the supplier, or the line is short shipped and corrected |
| Count mismatch | X-ray count against the reel or tray does not match the label | The count is repeated and reconciled, with the variance recorded rather than rounded away |
| Date code or shelf life | The code is older than the agreed window, or the part has a floor life | The code is inside the customer limit, or the parts are baked and the exposure clock is reset |
| Visual or X-ray defect | Bent leads, damaged reels, mixed parts in one pocket tape, voiding beyond the agreed limit | The defect is bounded by a sort, and the sorted quantity is counted |
| Suspect provenance | Marking, packaging or paperwork does not match the maker's normal presentation | Provenance is established from the supplier, or the material is rejected and returned |
| Handling exposure | Broken moisture barrier bag, missing humidity indicator, ESD packaging opened off station | Bake record to J-STD-033, or the material is consumed under a stated exposure allowance |
What the hold tag has to carry
The tag is read by people who were not there when the hold was raised, often in a hurry.
| Field | What it has to say |
|---|---|
| Hold number | A unique reference that ties the tag to the record in the system |
| Part number and maker part | Both, so an equivalent is not mistaken for the held item |
| Lot, date code and quantity held | The exact quantity stopped, and whether the reel was split |
| Location | The cage, shelf and bin, so a physical check is possible |
| Reason code | One of the six above, with one line of detail |
| Raised by and date | The person who stopped it, and the shift |
| Disposition and authority | What was decided, by whom, against which evidence |
| Release date and signature | The point at which the material became usable again |
A tag without a disposition is an open hold. A tag with a disposition but no authority is a release that nobody can defend.
Who can release, and on what authority
Release is a decision with a cost attached, so it belongs to whoever carries that cost. Four dispositions cover almost everything, and each has a level of authority that belongs in the procedure, not at the cage.
- Release as received. A query answered, and nothing about the material changed. Quality releases with the answer attached.
- Release after a bounded sort. A defect confirmed but limited, so the material is screened one hundred percent and the rejects replaced. Quality releases with the sort count recorded.
- Return to supplier. Material that cannot be made usable on site. Released to purchasing for return, against a debit note.
- Scrap. Unusable with no return route. Released by quality and finance together, because the value has to leave the books.
A fifth case exists: use as is with a known deviation. It is not a release in the ordinary sense, and it needs the customer's written agreement, never granted by the assembly supplier on the customer's behalf.
Four ways a hold leaks
The first is physical proximity. Material on hold stored beside released material gets picked eventually, because the person picking reads a kit list and not a tag.
The second is colour only. A tag with no entry in the stock system leaves the material available for allocation, so the next planning run reserves it.
The third is no expiry. A hold with no review date is closed by memory, and memory closes it in favour of the build.
The fourth is verbal release. Somebody senior says the parts are fine, the line runs, and the record still shows a hold. When the same lot fails in the field, the record says the material was never used.
How SUPERB PCBA holds and releases material
Incoming material is counted by X-ray against the reel or tray and compared to the purchase order before release to the line. Part number, quantity, date code and maker markings are checked in the same pass, so a documentation hold is raised at receipt rather than at the machine.
Moisture sensitive parts are stored with their floor life tracked and baked at 125 C to J-STD-033 when the exposure clock runs out. The SMT area runs under ESD S20.20 in an ISO 8 environment at 22 plus or minus 3 C and 45 to 65 percent relative humidity, and components carry a 730 day warranty from receipt.
Builds run through seven SMT lines with 01005 placement, 3D SPI, 3D AOI and X-ray to IPC-7095 with voiding under five percent, across a seventeen step flow with ten QC stations under IPC-A-610 Class 2 and Class 3. The quality system is ISO 9001, with ISO 13485 for medical work. A pin to pin substitute is used only with written customer approval, so a held part is never quietly replaced by an equivalent that clears the shortage and changes the build.
Component quarantine questions
Can material be released on a supplier certificate alone?
Only where the hold was raised on a document question and the certificate answers it. It cannot answer a count variance, a date code outside the window or a marking that does not match, because those are physical facts. The receipt checks are set out under incoming inspection plan.
Should a hold be raised for one damaged reel?
Yes, and it should be closed the same day. A hold raised and released quickly is a process that works; a damaged reel quietly set aside is a shortage nobody can explain. Shelf life and date code limits are covered under date code management.
What happens to held material when a build is brought forward?
Nothing, until the disposition is signed. A pulled in build date is not an authority to release, and treating it as one is how the same lot ends up in two records with two statuses. The line side is under kitting service.
Next step
Send the lot you are holding, the reason it was stopped and whatever the supplier has provided so far. The reply returns the disposition that the evidence supports, the fields that are missing from the tag, and the wording for a return or a bounded sort if the material cannot be released.