A component that has taken up moisture does not fail on the shelf. It fails in the reflow oven, where the trapped water turns to steam faster than the package can release it, and the body cracks or the die attach lifts. The crack is often invisible from the top, so the unit ships and fails months later in the field.
So moisture sensitivity level is a delivery item, not a datasheet footnote. A part that stayed open on a bench for a week is a different part from the one ordered, even when the reel, part number and date code match.
Where moisture control starts to slip
Three points decide the outcome, all before the oven: how the part was packed on arrival, how long it stayed out of the bag once opened, and whether it was baked before the reflow it faces.
Most moisture failures come from a missing clock, not a missing spec. A bag is opened on a Friday for a sample count, the parts go back on the shelf open, and the clock starts with nobody writing the time down. By the time the kit is picked, nobody can say how many hours the part has left.
Reading the level from the label
The label gives four facts: the level, the seal date, the floor life at that level, and the bake allowance once floor life is exceeded. The level is set by the package body and the die attach, so it belongs to the part and never to the build.
The clock starts at bag opening, not at delivery and not at kitting. A part with a 168 hour floor life that sat open 40 hours has 128 left, and that number belongs on the kit record because it decides whether the part goes to the line or bakes first.
A humidity indicator card is evidence about the trip, not the part. If it reads above its printed limit, the bag was breached between the seal and the shelf, and the parts count as exposed whatever the clock says.
Floor life by level
| Level | Floor life at 30 C and 60 % RH | What it means at kitting |
|---|---|---|
| MSL 1 | No limit | No clock and no bake |
| MSL 2 | One year | Nominal clock, still recorded |
| MSL 2a | Four weeks | open date recorded, no bake for a normal build |
| MSL 3 | 168 hours | Weekend exposure eats into the total |
| MSL 4 | 72 hours | Usually baked before a second reflow |
| MSL 5 | 48 hours | Counted per kit, not per reel |
| MSL 5a | 24 hours | Bake immediately before the run |
| MSL 6 | Time on the label | Bake is mandatory before use |
Those values assume 30 C and 60 % relative humidity. A humid floor shortens the real life while the label stays the same, which is why the ambient figure is written on the plan instead of assumed.
When baking is required, and which bake
Baking is required when the clock has run out, when the humidity card shows a breach, or when a part faces a second reflow its level does not allow. It is not routine: every bake is a thermal cycle, and the wrong one damages tape and reel, trays and labels.
| Situation | Method | What has to be watched |
|---|---|---|
| Body rated for 125 C | High temperature bake to J-STD-033 | Package body, and whether the carrier can take the heat |
| Trays, labels or low temperature parts | Low temperature bake at low humidity | Longer cycle, so the schedule has to hold the parts longer |
| Tape and reel | Bake in the carrier only when the carrier is rated for it | Reel deformation and cover tape adhesion |
| Batteries and thermal-limited parts | Not baked, replaced | A battery in a 125 C oven is scrap, not a shortcut |
A bake resets the floor life clock, not the part's total bake allowance. The body has been through one more thermal cycle, and that count belongs on the record too.
What the bake record has to carry
Six facts make the record usable at an audit or a field return, and they take a minute: part number and lot, the level from the label, hours already used against floor life, bake method with temperature and time, quantity and carrier, and who released the parts back to the line with the new expiry.
With those six, a field failure traces back to whether its parts were inside their moisture budget at reflow. Without them, the answer is a claim.
How SUPERB PCBA handles moisture control
Incoming parts are checked for part number, quantity, date code and maker markings before release, and the moisture label goes into the kit record at the same time, so the clock and the bag open on one day. Kits for RF, medical and military builds stay in a controlled store, not on the line.
Baking runs at 125 C to J-STD-033 where the package and carrier allow it, and at low temperature where they do not. The bake log is attached to the work order, and the reflow that follows is a twelve zone nitrogen oven under 500 ppm oxygen with a SAC305 profile, so the cycle the part sees is the one the profile states.
The build runs seven SMT lines with 01005 placement, 3D SPI after print, 3D AOI after reflow and X-ray to IPC-7095 with voiding under five percent, through a seventeen step flow with ten QC stations under IPC-A-610 Class 2 and Class 3, under ISO 9001 and ISO 13485 for medical work. Where a part arrives with no moisture data, the kit is held and the question raised before the run.
Component MSL and bake control questions
Can a part be baked inside its tape and reel?
Only when the carrier is rated for the temperature. Most tape deforms or loses cover tape adhesion, and the reel jams at the feeder, which costs more than the bake saved. Matrix trays are safer for a high temperature bake. How parts are held before release is covered under component quarantine, hold and release.
Does a part that passes the humidity card need baking?
No baking is needed when the card reads inside its limit and the clock is still running. The card proves the bag held, the clock proves the exposure since opening, and neither replaces the other.
Who owns the moisture data when a part comes from a surplus lot?
Nobody, until it is asked for. Parts from outside the normal channel often arrive without the original bag or label, so the level comes from the datasheet rather than a bag that does not exist, and where it cannot be established the part is treated as the worst case in its family and baked. The method is summarised under MSL moisture sensitivity, and the floor life side under MSL floor life and baking before reflow.