A purchase order leaves the building and then goes quiet. The supplier has it, the buyer has a number in a system, and the first real news arrives weeks later when the promised date passes with no ship notice attached. By then the only options left are the expensive ones: air freight, a broker, or a build moved back.
Follow-up is not a reminder email sent when someone remembers. It is a short sequence of questions asked at fixed points, each one written to turn an assumption into a confirmed fact before the material is needed on the line.
Why a purchase order goes quiet
Three things cause most of the silence. An order can be received without being accepted, so the system shows a status while nobody has committed to a date. A line can be confirmed for a quantity the supplier cannot cover in one shipment, which makes the date real for part of the order and fictional for the rest. And an order can sit in a queue behind someone else's allocation, where the supplier has no reason to volunteer that the position changed.
None of these is visible from inside a purchasing system, because the system records what was sent rather than what was agreed.
The states a purchase order actually passes through
Every line is in one of eight states, and only one of them tells you anything about whether the build will run.
| State | What it proves | What it does not prove |
|---|---|---|
| Issued | The order left your side | That anyone at the supplier has seen it |
| Received | The order exists in their system | That capacity has been reserved for it |
| Acknowledged | Someone replied | That the reply carries a date or a quantity |
| Partially confirmed | Part of the quantity has a date | Anything about the remainder |
| Confirmed with ship date | Full quantity against a written date | That the date will hold if allocation tightens |
| Shipped | Material is moving | That the quantity and part number match the order |
| Received at dock | The cartons arrived | That the contents are what was ordered |
| Accepted after inspection | Quantity, marking and date code verified | Nothing further, this is the state that counts |
The question that matters moves a line from state two to state five: what date, for what quantity, confirmed by whom.
A follow-up schedule that catches slippage early
The cadence matters more than the wording, and it has to suit a twelve to twenty six week lead time.
| Point | Question to ask | What the answer decides |
|---|---|---|
| Day 0, at issue | Request a written acknowledgement with a ship date inside three working days | Whether the order landed in a queue or with a planner |
| Day 3 | Is the date based on stock, on a scheduled build, or on a wafer or tooling start | How much notice you will get if the date moves |
| Day 7 | Is the full quantity covered by that date, or is it a partial | Whether a split shipment has to be planned now |
| Day 14 | Has the date moved since acknowledgement, and why | First real read on supply position |
| Day 28 | Is the part still on the same date, and is there an approved equivalent if not | Whether to start the alternate route while there is still time |
| Need date minus lead time | Is a ship notice issued, with tracking | Whether the build runs or the schedule moves |
The questions are asked whether or not there is news, so a supplier cannot buy quiet by staying quiet, and every answer is written down.
What to record on every follow-up
A follow-up log with six fields is enough: the confirmed ship date, the quantity it covers, whether the line is a partial, how many times the date has moved, who confirmed it and in which channel, and whether an alternate was offered.
Two reschedules on the same line is not bad luck, it is a supply position that has changed, and it moves the line from chasing to escalation. A third reschedule usually means the part is short in the market rather than late in a queue, and the decision becomes a last time buy or a bill of material change.
How SUPERB PCBA keeps purchase orders under control
Material is counted by X-ray against the reel or tray on receipt rather than trusted by label, and the count is reconciled against the purchase order before the line sees it. Part number, quantity, date code and maker markings are compared at the same time, so a shipment that arrives in the right carton with the wrong contents is caught on the dock rather than at the machine.
Parts with a shelf life carry a date code and a storage class in the record, moisture sensitive parts are baked at 125 C to J-STD-033, and material is held under ESD S20.20 in an SMT area at ISO 8, 22 plus or minus 3 C and 45 to 65 percent relative humidity. Components carry a 730 day warranty from receipt.
The assembly side runs seven SMT lines with 01005 placement, 3D SPI, 3D AOI, X-ray to IPC-7095 with voiding under five percent, and a seventeen step flow with ten QC stations under IPC-A-610 Class 2 and Class 3, ISO 9001 and ISO 13485. When a purchase order slips, the question a customer actually needs answered is what can still be built this week, and that answer comes from a counted kit rather than an open order list.
When a purchase order has to be escalated
Escalation goes better when it opens with the constraint rather than the complaint. Three routes exist: resequence the build around the missing part, split the kit so the boards that do not need it ship on time, or qualify a cross referenced equivalent with the customer's written approval and a check that package, pinout, tolerance and temperature grade match.
A broker route is the last option, and it only makes sense with incoming verification: X-ray count and marking check on every reel.
Purchase order follow-up questions
How often should an open order be chased?
At fixed points rather than whenever someone worries: day three, day seven, then weekly until a ship notice exists. Predictable questions get answered; irregular ones get filtered.
Is a supplier portal status field enough?
It is enough to know an order exists, not that a date is committed, because the field usually reflects receipt rather than capacity. Ask for the confirmation in writing. The lead time side is set out under component lead time solutions.
What if the supplier ships a partial quantity?
Accept it only with a dated plan for the balance, and record the split so kitting does not assume the full quantity. A partial without a second date is a shortage with better paperwork. The recovery sequence is in BOM shortage recovery.
Next step
Send the open purchase orders with the confirmed dates you hold, the build schedule they feed, and the parts where a date has already moved. The reply returns the lines with no confirmed date, the quantity gaps behind the confirmed ones, and where an approved equivalent removes the exposure. For the quotation side, see PCBA quote checklist.