A high mix line does not lose money while it runs. It loses money between runs. Twenty boards of one product and twenty of another cost more than forty of the same board, and the difference is almost never placement time. It is the stencil, the kit, the first article, the profile and the paperwork that each build needs before a single part is placed.
For a buyer, that gap shows up as a quote that looks high on a small lot, or as a date that slips by three days because one line item in the kit arrived short. Both are setup problems, and both are manageable once the setup is treated as the product.
Where a small lot spends its time
Five steps repeat for every build, whatever the quantity: stencil and tooling, kit and verification, machine setup and profile, first article and approval, then traceability and packing. On a run of five hundred boards those steps are spread thin. On a run of twenty they are the whole job.
The most common surprise is not the stencil, which everybody expects. It is the kit. A BOM of two hundred lines on a build of twenty boards still needs two hundred lines verified, and a single wrong reel discovered at first article costs more than the whole run.
What changes between a volume run and a mixed lot
| Item | Volume run | High mix low volume |
|---|---|---|
| Stencil and tooling | Amortised over a long run | Per build, and often the largest single line in the quote |
| Kit verification | Reels run for days | Every line checked per lot, usually by X-ray count and a sample check |
| Profile | One profile per product family | One profile per build, with a thermocouple run when the stack changes |
| First article | Once per product | Once per lot, and it gates the rest of the run |
| Line balance | Placement dominated | Setup dominated, so the sequence matters more than the takt time |
| Traceability | Lot level | Often unit level, with serials and a break record |
The setup items that decide the date
Six items, in the order they usually cause a slip. Each one is cheap to fix a week early and expensive to fix on the day.
| Item | What has to be settled before the build starts |
|---|---|
| Stencil | Aperture pattern for the fine pitch parts, thickness, and whether a step stencil is needed for a mixed paste demand |
| Kit | Approved maker and part number per line, plus the written rule for an alternative |
| Moisture | Which parts are moisture sensitive, and whether the lot needs a bake before the run |
| Profile | The thermocouple run for the actual stack, not the last product that looked similar |
| Test | Fixture, limits and who signs the first article |
| Packing | Serial format, label content, and the ESD packing the customer's own line expects |
How SUPERB PCBA handles small lots
The work is build to print: you release the package, we hold the process. Seven SMT lines take 01005 parts up to odd form connectors of 55 to 57 mm, with 3D SPI after print, 3D AOI after reflow, DIP AOI and X-ray read to IPC-7095 with voiding under five percent. Reflow is a twelve zone nitrogen oven under 500 ppm oxygen with SAC305.
Component supply comes through authorized channels, with the maker and part number bought to your approved list, X-ray counting on incoming reels and a sample check on markings. The kitting side is described under kitting service, and the quote items that have to be listed separately for a small lot are set out under PCBA quote checklist.
Test is functional on a fixture built to your spec, with ICT on a bed of nails or flying probe where the board allows it. The flow is seventeen steps with ten QC stations, held to IPC-A-610 Class 2 and Class 3, under ISO 9001 and ISO 13485 for medical work. Placement capacity per line is up to 40,000 components per hour, which matters less on a small lot than changeover discipline does, and the chip shooter side is described under high speed chip shooter.
What to put in the request for a mixed lot
Quantity per build, how many builds share the order, and whether they ship together or as they finish. Then the package per build, the approved list, and the test spec. Those three decide whether the lot runs as one job or as four, and that difference is visible in both price and date.
It also helps to say which items can be substituted and which cannot. On a mixed lot the shortage risk concentrates in the long lead lines, and a written substitution rule lets the build start on time instead of waiting for one reel.
High mix low volume questions
Is there a minimum quantity?
There is a minimum that makes the setup worth running, and it moves with the package: a single sided board with forty lines and a double sided board with four hundred lines do not sit at the same point. Send the BOM and the quantity you have in mind, and the quote shows the setup as its own line so the number is visible instead of hidden in the unit price.
Can several small builds share one order?
Yes, and it usually saves money, because the paperwork and the incoming inspection are done once. Each build still gets its own kit, its own stencil, its own first article and its own traceability record, so sharing an order does not blur which board is which.
How is a repeat build handled?
The process record from the first lot is kept: stencil, profile, paste window, fixture and the deviations that were approved. A repeat runs from that record instead of from scratch, which is why a second lot of twenty is usually cheaper than the first.