A supplier passes the quality audit, wins the business, and then misses the second quarter. Nothing in the audit predicted it, because a quality audit asks whether the process is controlled, not whether the line has room for the volume.

A supplier capacity assessment answers one question: on the date this volume arrives, is there a line, a shift and a set of tools free to run it. The answer comes from numbers, not from a site tour.

What a capacity assessment is not

It is not a certificate count and it is not a list of machines. A plant with ten lines and one shift has the same weekly capacity as a plant with five lines and two shifts, and the second one is usually easier to schedule because the second shift already exists.

It is also not a single number. Capacity is a curve against product mix, because a line that runs 01005 placement at high speed cannot run the same rate on a board with a 55 mm connector and a selective coating step. The useful answer is a range with the mix stated.

The six numbers to ask for

NumberWhat it tells youRed flag
Committed load next quarter, in line hoursHow much of the capacity is already soldNo figure available, only a promise
Utilisation at the bottleneck, not the averageWhere the queue will formAverage utilisation quoted, bottleneck unnamed
Changeover time for your product familyHow much of a shift is lost to setupSame changeover claimed for every family
Queue time before placement and before testThe real lead time, split by stageOne lead time quoted for the whole build
Yield and rework rate on similar buildsEffective capacity after rework eats itYield quoted without a build reference
Escalation path when load exceeds planWhat happens on the bad weekNo second shift, no partner site, no plan

Ask for the same six numbers for the two quarters after the one you care about. Capacity that exists for your launch and disappears in the following quarter is a ramp risk, and it is cheaper to find it now.

How to read the answers

Utilisation above 85 percent at the bottleneck means the date you are given already assumes perfect weeks. Between 60 and 80 percent there is room for a slip. Below 50 percent the question changes from capacity to continuity, because a line that is half empty may not be there in a year.

Queue time is the number that decides promise dates, and it is usually the one withheld. A placement queue of two days and a test queue of four days explains a lead time of eight working days on a build that takes two days to run. When a supplier quotes a single lead time with no split, the split is being absorbed somewhere, and it will show up as a late week later.

Changeover is where small orders lose money. A family that needs a stencil change, a paste change and a reflow profile change can consume most of a shift, so a supplier who can batch your family with a similar build will quote a shorter date than one who runs it alone.

How SUPERB PCBA schedules capacity

Assembly runs on 7 SMT lines in a 5,000 square metre static controlled workshop, with placement down to 01005 and a stated daily placement figure of 15.32 million components. The SMT area is held at ISO 8 with 22 plus or minus 3 degrees and 45 to 65 percent humidity, under ANSI/ESD S20.20 handling and 17 step production flow with a 10 station quality line.

Load is planned against the customer forecast rather than against the last order, so a ramp is quoted with the shift pattern it needs. Where a build needs a fixture, the functional test fixture is prepared before the run, because a fixture built after the boards arrive is the most common cause of a missed first date. Moisture sensitive parts are baked at 125 degrees per J-STD-033 so the reflow window is not lost waiting for a bake.

For programmes that need a second route, the bare board side is covered by our own PCB workshops and by audited partner board shops, and the assembly commitment is written per quarter rather than per order. The paper trail behind that commitment is the same one a customer audit reads: supplier scorecard, supplier quality audit and material requirements planning.

The honest limit is worth stating at the start. Capacity on a single line is finite, and a request that doubles volume inside one quarter is answered with a date, not with a promise. Medical builds run under ISO 13485 and the rest under ISO 9001, with IPC-A-610 Class 2 or Class 3 as specified, and the capacity reserved for a medical programme is not moved to a commercial build without the customer being told.

Common questions

How far ahead should capacity be booked?

One quarter for a stable programme, two for anything with a launch date. The booking is a stated monthly volume with a tolerance band, not a firm order, so the line can be planned without holding material.

Can a capacity assessment be done without a site visit?

Yes for the numbers, no for the bottleneck. The six figures can be exchanged in a day. Confirming which station is the bottleneck, and how the queue behaves in a bad week, is what a visit settles.

What happens when actual volume comes in below the forecast?

The reserved capacity is released at the next review rather than held empty, and the build dates already given do not move. Under-use is reported rather than hidden, because a forecast that is never corrected is worse than no forecast.

Next step

Send the monthly volume by product family, the launch date, the board size and layer count, the placement count per board and the test steps you need. SUPERB PCBA replies with the line, the shift pattern and the queue time assumed for that volume, so the date can be checked against a plan rather than a hope.