A bill of materials looks finished the moment it opens in a spreadsheet. Every line has a part number, a quantity and a reference position, and the file has a version at the top. Then the build starts and the problems appear in the least convenient places: a reel of the right family in the wrong package, a line whose quantity was copied from a ten year old build, a part that the maker stopped shipping two quarters ago.

BOM scrubbing is the pass that happens before a quotation or a kitting list exists. It reads every line as an instruction to buy and to place, and it assumes nothing in the file is correct until the line has been checked against the maker data, the land pattern on the board and the quantity the build actually consumes.

Why a BOM fails after it has been signed off

Most bad lines are inherited rather than created. A board is revised, the circuit changes, the BOM is exported, and the old alternates stay attached to the new lines. A purchasing team adds a cheaper equivalent without a written note. A suffix disappears in a copy and paste, and a commercial temperature part now sits where an industrial one used to be.

The result is not a failed build in the obvious sense. It is a build that runs, ships, and then fails in the field at a rate nobody can explain, or a line stop on the second run when the substituted part is no longer on the shelf.

What scrubbing checks on every line

The work is repetitive by nature, which is why it has to be a fixed list rather than a judgement call.

CheckWhat goes wrong without it
Exact part number and suffixTemperature range, package or packing option quietly changes
Package against the land patternPart fits the reel but not the pads on the board
Quantity against build size and attritionShortfall appears at the end of the run, not the start
Lifecycle statusLine is bought just as the maker moves it to end of life
Alternates with written approvalSilent substitution invalidates the customer approval
Date code and moisture levelParts need baking before reflow, or are outside acceptance
Finish and compliance statusLead free requirement missed on one line only
Reference position duplicates and gapsTwo parts placed at one position, or one position left empty

Each check is cheap on its own. Together they take a fraction of the time a line stop costs, and they are the reason a scrubbed BOM quotes faster than an unscrubbed one.

How scrubbing changes the quote and the build

A scrubbed BOM produces a different set of questions, and those questions arrive before the order rather than after it.

FindingWhat scrubbing does with it
Part is end of life or last time buyQuantity is set for the full demand window, not the first run
Part is on allocationAn approved equivalent is proposed with a written comparison
Alternate has a different footprintFlagged before tooling, so the pad change is decided early
Quantity assumes zero attritionReel and tray waste is added per line, not guessed at the end
Two lines are the same partMerged into one purchase position, so the price break is reached
Date codes are mixedOldest stock is consumed first and recorded on the build

How SUPERB PCBA runs the scrubbing pass

Every line is matched to the part maker data sheet and to the Gerber before a price is issued. Where a line cannot be confirmed, it is queried rather than assumed: the customer sees the specific question, not a general note that the BOM has issues.

Sourcing runs against traced supply rather than open market listings. Incoming material is counted by X-ray reel counter and checked for marking, and where a part is suspect, decapsulation and die verification settle it. Parts carry a 730 day warranty from delivery. Where a line is affected by an end of life notice, the last time buy quantity is calculated against the customer forecast and agreed in writing.

Substitution is never silent. A pin to pin equivalent is proposed with the parameters that differ, and it is placed only after the customer approves in writing. This matters most on radio frequency boards, where a part that looks equivalent on paper can shift gain or noise figure by an amount that only shows up in the customer laboratory.

The assembly side of the check uses the same data: 7 SMT lines, component placement down to 01005, 3D solder paste inspection, post reflow AOI, DIP AOI and X-ray with void acceptance under 5 percent per IPC-7095. Moisture sensitive parts are baked at 125 degrees per J-STD-033 before reflow. Builds run to IPC-A-610 Class 2 or Class 3 as specified, under ISO 9001, and ISO 13485 for medical work. The sequence behind a scrubbed BOM is set out in one stop BOM sourcing, and the quantity side is covered in BOM consolidation.

Common questions

How long does a scrubbing pass take?

A board with 300 lines is normally answered within one working day when the file is clean, and the same day if the customer is available to answer queries. Files with many unapproved alternates take longer, because each one needs a written decision before it can be priced.

Can a BOM be scrubbed without a Gerber?

Partly. Part numbers, quantities, lifecycle and date code can all be checked from the BOM alone. Package against land pattern cannot, because the pad geometry lives on the board. Send both and the package check is included; send the BOM only and that one line of the check stays open.

What if a line has no approved alternate and the part is gone?

Then the decision moves to the customer: a functional equivalent with a stated difference, a last time buy from remaining stock, or a board change. SUPERB PCBA proposes options with parameters side by side and does not place any of them without written approval. Stock age and traceability are handled as described under date code management.

Next step

Send the BOM, the Gerber revision it belongs to, the build quantity and the date the boards are needed. The reply returns the lines that cannot be confirmed, the lines where an approved equivalent removes a lead time risk, and a price for the quantity actually required rather than the quantity in the file.